Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.95 | 0.95 | 0.000 | 0.95 | 0.950 | 0.000 |
55W1906 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O.No. 1/164806/2023 PWD2-BUD/1/2023-III-2-Public Works Department
TS Amount (lakhs) : 51.26 Lacs
Financial Detail
Sanction Cost : 51.26 Lacs
Resanction Cost : 51.26 Lacs
Exp. Upto Last Fy : 10.61 Lacs
For CFY 2024-2025
Remaining : 40.65 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 10.61 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 2 %
Sanction on :
6 months 3 weeks ago
27 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में है। -- as on 28-Mar-2024