Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.63 | 1.63 | 0.000 | 1.63 | 1.630 | 0.630 |
55W1907 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/186272/2024/पीडब्लूडी2-बीयूडी/ एएनबीयू/36/2023-।।।-2-लो0नि0वि0
TS Amount (lakhs) : 69.67 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
69.67
Resanction Cost :
69.67
Tentative Cost :
69.67
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 69.67
Demand : 40.00
Allotment : 20.00
Exp in CFY : 16.75
Total Up to Date Exp : 16.75
Construction Started
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 38 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
4 weeks 19 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.63 कि0मी0 में कार्य पूर्ण, शेष लम्बाई में ग्रामीणों द्वारा मार्ग के लेविल सम्बन्धी विवाद किया गया जिसको माह जून 2024 में प्रशासन व स्थानीय ग्रामीणों के साथ वार्ता कर सुलझा लिया गया है, कार्य शीघ्र ही पूर्ण कर लिया जायेगा। -- as on 01-Jul-2024
Physical Peramenters