Work Profile Report [55W1915]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/197290/2024/PWD2-BUD/ANBU/12/2024-III-2-Public Works Department
TS Amount (lakhs) : 49.33 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
49.33
Resanction Cost :
49.33
Tentative Cost :
49.33
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
49.23
Demand :
20.00
Allotment :
9.79
Exp in CFY :
9.79
Total Up to Date Exp :
9.89
Construction Started
Sanction on : 9 months 1 week ago
11 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
51 %
Tentative Completion date on : 2 months 3 weeks from now
15 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.45 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 26-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand