Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.7 | 1.7 | 0.000 | 1.7 | 1.700 | 1.000 |
55W1917 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/197578/2024/PWD2-BUD/ANBU/19/2023-III-2-Public Works Department
TS Amount (lakhs) : 91.46 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
91.46
Resanction Cost :
91.46
Tentative Cost :
91.46
Exp. Upto Last Fy : 0.11
For CFY 2024-2025
Remaining : 91.35
Demand : 45.14
Allotment : 40.00
Exp in CFY : 39.16
Total Up to Date Exp : 39.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 58 %
Sanction on :
4 months 5 days ago
12 Mar 2024
Tentative Completion date:
2 days 18 hours from now
20 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.00 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 29-Jun-2024
Physical Peramenters