Work Profile Report [55W1947]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/239986/2024/PWD2-BUD/ANBU/32/2023-III-2-Public Works Department
TS Amount (lakhs) : 41.19 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41.19
Resanction Cost :
41.19
Tentative Cost :
41.19
Exp. Upto Last Fy :
14.27
For CFY 2025-2026
Remaining :
26.92
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
14.27
Work completed
Sanction on : 7 months 2 weeks ago
13 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
100 %
Tentative Completion date on : 1 month 2 days from now
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 04/2025 -- as on 28-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: