Work Profile Report : 55W2056
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/352909/2025/PWD2-BUD/ANBU/17/2025-III-2-Public Works Department Dt. 15-12-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
94.26
Resanction Cost :
94.26
Tentative Cost :
94.26
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
94.26
Demand :
10.00
Allotment :
31.99
Exp in CFY :
31.99
Total Up to Date Exp :
31.99
Construction Started
Sanction on : 1 month 4 weeks ago
15 Dec 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
40 %
Tentative Completion date on : 7 months 2 weeks from now
30 Sep 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.40 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 03-Feb-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: