Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 |
56W141 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5150 (1)/।।। -2/10-18(प्रा0आ0)/10 दि0 16.8.10
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
31.50
Resanction Cost :
31.50
Tentative Cost :
31.50
Exp. Upto Last Fy : 26.33
For CFY 2024-2025
Remaining : 5.17
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 26.33
Survey work done
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
13 years 10 months ago
18 Aug 2010
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
अपर सचिव उत्तराखण्ड़ शासन के पत्रांक संख्या 431(1)ध्एक्स-49-19ध्1(348)2015 दिनांक 25.11.2019 द्वारा विधित स्वीकृति स्वीकृति प्राप्त। भूमि प्रतिकर की कार्यवाही गतिमान। -- as on 06-Apr-2024
Physical Peramenters