Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 9 | 0 |
56W21 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-3038/111-(2)/06-07 (प्रा0आ0)/2005 दि0 8.11.2006
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
145.80
Resanction Cost :
145.80
Tentative Cost :
145.80
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 145.80
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
17 years 8 months ago
08 Nov 2006
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
विवाद सुलाझ लिया गया है संरेखण कार्य प्रगति पर है। -- as on 27-Dec-2021
Physical Peramenters