Work Profile Report [56W620]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2385/।।।(2)/21-37(प्रा0आ0)2013 दिनांक 04.08.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
119.42
Resanction Cost :
119.42
Tentative Cost :
119.42
Exp. Upto Last Fy :
98.01
For CFY 2024-2025
Remaining :
21.41
Demand :
21.41
Allotment :
21.80
Exp in CFY :
21.80
Total Up to Date Exp :
119.81
Work completed
Sanction on : 3 years 4 months ago
04 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
माह मार्च 2024 में भौतिक रूप से 5.00 किमी0 में कार्य पूर्ण। दायित्व का भुगतान शेष। -- as on 06-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: