Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
56W620 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2385/।।।(2)/21-37(प्रा0आ0)2013 दिनांक 04.08.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
119.42
Resanction Cost :
119.42
Tentative Cost :
119.42
Exp. Upto Last Fy : 98.01
For CFY 2024-2025
Remaining : 21.41
Demand : 21.41
Allotment : 19.00
Exp in CFY : 17.19
Total Up to Date Exp : 115.20
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
माह मार्च 2024 में भौतिक रूप से 5.00 किमी0 में कार्य पूर्ण। दायित्व का भुगतान शेष। -- as on 06-Apr-2024
Physical Peramenters