Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 160 | 130 | 130.000 | 0 | 0.000 | 0.000 |
56W690 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिओ नम्बर 2451/।।।(2)/23-01(प्रा0आ0)/2019 दिनांक 21 जुलाई, 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
719.43
Resanction Cost :
719.43
Tentative Cost :
719.43
Exp. Upto Last Fy : 683.93
For CFY 2024-2025
Remaining : 35.50
Demand : 35.50
Allotment : 20.00
Exp in CFY : 17.15
Total Up to Date Exp : 701.09
none
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
3 weeks 5 days ago
21 Jun 2024
Actual Completion Date:
4 months 1 week ago
04 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व का भुगतान शेष। -- as on 06-May-2024