Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 0.000 | 2.2 | 2.200 | 2.200 |
56W692 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के ई-प्रत्रावली संख्या 63074 दिनांक 18.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
76.32
Resanction Cost :
76.32
Tentative Cost :
76.32
Exp. Upto Last Fy : 6.96
For CFY 2024-2025
Remaining : 69.36
Demand : 55.58
Allotment : 42.00
Exp in CFY : 40.33
Total Up to Date Exp : 47.29
none
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 91 %
Sanction on :
6 months 4 weeks ago
18 Dec 2023
Tentative Completion date:
4 months 3 weeks from now
14 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.00 किमी0 में पहाड कटान का कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 27-Jun-2024
Physical Peramenters