Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
56W78 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1754/111/-(2)/05-64(प्रा0आ0)/05 दि0 10/11/05
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 69.50 Lacs
Resanction Cost : 69.50 Lacs
Exp. Upto Last Fy : 56.89 Lacs
For CFY 2024-2025
Remaining : 12.61 Lacs
Demand : 8.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 56.89 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
18 years 6 months ago
10 Nov 2005
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
भारत सरकार पर्यावरण एवं वन मंत्रालय के पत्रांक संख्या 8बी0/यू0सी0पी0/06/52/2016एफ0सी0/1162 दिनांक 04.09.2020 को सैद्धान्तिक स्वीकृति प्रापत अधिशासी अभियन्ता के पत्र संख्या 1441/6सी. दिनांक 04.08.2022 के द्वारा विधिवत स्वीकृति हेतु पुनः प्रभागीय वनाधिकारी चकराता को पत्र प्रेषित पहाड कटान का कार्य किया जा राहा है मुख्य अभियन्ता लो0नि0वि0 के पत्रांक संख्या 603/09(208)याता0-स्तर-।(क्षे0का0)/2022 दिनांक 06.02.2023 के द्वारा लम्बाई 4.70किमी0 लागत रू0 286.60 लाख का पुनरीक्षित आगणन नई दरों पर गठित कर प्रमुख सचिव, लो0नि0वि0 देहरादून शासन को प्रेषित। -- as on 06-Apr-2024
Physical Peramenters