Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.4 | 3.4 | 3.4 | 0 |
59W1760 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 1255/।।।(2)/19-30(एम0एल0ए0) /2017 दि0 06.03.2019
TS Amount (lakhs) : 184.39 Lacs
Financial Detail
Sanction Cost : 205.02 Lacs
Resanction Cost : 205.02 Lacs
Exp. Upto Last Fy : 143.82 Lacs
For CFY 2024-2025
Remaining : 61.20 Lacs
Demand : 50.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 143.82 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 2 months ago
06 Mar 2019
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्वों का भुगतान शेष। -- as on 25-Apr-2024
Physical Peramenters