Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.02 | 2.02 | 2.02 | 0 |
59W1978 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5964(1)/।।।(2)/21-29(एम.एल.ए.) /2017टी.सी.-। देहरादून दि0 09.12.2021
TS Amount (lakhs) : 71.05 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
71.05
Resanction Cost :
71.05
Tentative Cost :
71.05
Exp. Upto Last Fy : 62.52
For CFY 2024-2025
Remaining : 8.53
Demand : 8.00
Allotment : 0.00
Exp in CFY : 6.90
Total Up to Date Exp : 69.42
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
09 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्वों के भुगतान शेष। -- as on 18-Apr-2023