Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.275 | 1.275 | 1.200 | 0.075 | 0.070 | 0.000 |
59W2108 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-50282 दिनांक 28.03.2023
TS Amount (lakhs) : 53.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
53.15
Resanction Cost :
53.15
Tentative Cost :
53.15
Exp. Upto Last Fy : 23.39
For CFY 2024-2025
Remaining : 29.76
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 23.39
Construction Started
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
1 week 4 hours ago
10 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.200 किमी0 में पी0सी0 कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 05-Dec-2023
Physical Peramenters