Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 80 | 80 | 0.000 | 80 | 80.000 | 0.000 |
59W2110 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-45824 दिनांक 29.03.2023
TS Amount (lakhs) : 394.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
394.19
Resanction Cost :
394.19
Tentative Cost :
394.19
Exp. Upto Last Fy : 161.53
For CFY 2024-2025
Remaining : 232.66
Demand : 200.00
Allotment : 73.00
Exp in CFY : 0.92
Total Up to Date Exp : 162.45
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 80 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सेतु के दोनों ओर के ए-1 एवं ए-2 पर एबटमेंट कैप का कार्यपूर्ण एवं फैब्रीकेशन का कार्य प्रगति में। (80 प्रतिशत कार्यपूर्ण) -- as on 27-Jun-2024
Physical Peramenters