Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.515 | 0.515 | 0.515 | 0 |
59W2116 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-53391 दिनांक 14.07.2023
TS Amount (lakhs) : 22.08 Lacs
Financial Detail
Sanction Cost : 22.08 Lacs
Resanction Cost : 22.08 Lacs
Exp. Upto Last Fy : 14.74 Lacs
For CFY 2024-2025
Remaining : 7.34 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 14.74 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 months 5 days ago
14 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्वों का भुगतान शेष। -- as on 25-Apr-2024
Physical Peramenters