Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.58 | 1.58 | 0.800 | 0.78 | 0.780 | 0.780 |
59W2120 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-47887 दिनांक 19.07.2023
TS Amount (lakhs) : 45.22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
45.22
Resanction Cost :
45.22
Tentative Cost :
45.22
Exp. Upto Last Fy : 10.98
For CFY 2024-2025
Remaining : 34.24
Demand : 22.00
Allotment : 5.68
Exp in CFY : 28.35
Total Up to Date Exp : 39.33
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 04/2024 -- as on 03-May-2024