Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.94 | 0.94 | 0.94 | 0 |
59W2122 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667 दिनांक 27.07.2023
TS Amount (lakhs) : 86.98 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
86.98
Resanction Cost :
86.98
Tentative Cost :
86.98
Exp. Upto Last Fy : 73.73
For CFY 2024-2025
Remaining : 13.25
Demand : 13.00
Allotment : 11.88
Exp in CFY : 11.88
Total Up to Date Exp : 85.61
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
27 Jul 2023
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्वों का भुगतान शेष। -- as on 25-Apr-2024
Physical Peramenters