Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.94 | 0.94 | 0.94 | 0 |
59W2122 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667 दिनांक 27.07.2023
TS Amount (lakhs) : 86.98 Lacs
Financial Detail
Sanction Cost : 86.98 Lacs
Resanction Cost : 86.98 Lacs
Exp. Upto Last Fy : 73.73 Lacs
For CFY 2024-2025
Remaining : 13.25 Lacs
Demand : 13.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 9.80 Lacs
Total Up to Date Exp : 83.53 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 months 3 weeks ago
27 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्वों का भुगतान शेष। -- as on 25-Apr-2024