Length of Road [Km] | 1.3 | 1.3 | 0.400 | 0.9 | 0.900 | 0.900 |
59W2129 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435 दिनांक 31.07.2023
TS Amount (lakhs) : 94.17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
94.17
Resanction Cost :
94.17
Tentative Cost :
94.17
Exp. Upto Last Fy : 31.75
For CFY 2024-2025
Remaining : 62.42
Demand : 38.00
Allotment : 2.52
Exp in CFY : 37.86
Total Up to Date Exp : 69.60
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 month 2 days ago
15 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2024 -- as on 27-Jun-2024