Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 0.100 | 1.1 | 1.100 | 0.125 |
59W2131 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435 दिनांक 31.07.2023
TS Amount (lakhs) : 44.07 Lacs
Financial Detail
Sanction Cost : 44.07 Lacs
Resanction Cost : 44.07 Lacs
Exp. Upto Last Fy : 0.06 Lacs
For CFY 2024-2025
Remaining : 44.01 Lacs
Demand : 32.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 9.40 Lacs
Total Up to Date Exp : 9.45 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
8 months 2 weeks ago
31 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.125 किमी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 03-May-2024
Physical Peramenters