Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.58 | 1.58 | 0.200 | 1.38 | 1.000 | 0.000 |
59W2132 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435 दिनांक 31.07.2023
TS Amount (lakhs) : 51.74 Lacs
Financial Detail
Sanction Cost : 51.74 Lacs
Resanction Cost : 51.74 Lacs
Exp. Upto Last Fy : 17.31 Lacs
For CFY 2024-2025
Remaining : 34.43 Lacs
Demand : 22.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 17.31 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 17 %
Up to Date : 17 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में है। -- as on 05-Jan-2024
Physical Peramenters