Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.948 | 2.948 | 0.500 | 2.448 | 1.550 | 1.550 |
59W2136 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-53469 दिनांक 07.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
123.82
Resanction Cost :
123.82
Tentative Cost :
123.82
Exp. Upto Last Fy : 49.61
For CFY 2024-2025
Remaining : 74.21
Demand : 70.00
Allotment : 0.00
Exp in CFY : 1.00
Total Up to Date Exp : 50.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 23 %
Up to Date : 80 %
Sanction on :
11 months 1 week ago
07 Aug 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.05 किमी0 में सी0सी0 टाईल्स कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 27-Jun-2024
Physical Peramenters