Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.08 | 0.08 | 0.08 | 0 |
59W2147 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी, हरिद्वार के पत्रांक- 662/8-डी.पी. -02/जि0यो0-(संरचना)/2023-24 दि0 04.08.2023
TS Amount (lakhs) : 6.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
6.91
Resanction Cost :
6.91
Tentative Cost :
6.91
Exp. Upto Last Fy : 3.15
For CFY 2024-2025
Remaining : 3.76
Demand : 3.76
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.15
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
04 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्वों का भुगतान शेष। -- as on 25-Apr-2024
Physical Peramenters