Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.11 | 1.11 | 1.000 | 0.11 | 0.110 | 0.110 |
59W2197 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-47887 दिनांक 04.10.2023
TS Amount (lakhs) : 41.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.87
Resanction Cost :
41.87
Tentative Cost :
41.87
Exp. Upto Last Fy : 24.86
For CFY 2024-2025
Remaining : 17.01
Demand : 17.00
Allotment : 11.58
Exp in CFY : 15.77
Total Up to Date Exp : 40.63
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
9 months 1 week ago
04 Oct 2023
Tentative Completion date:
1 month 3 weeks ago
24 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 05/2024 -- as on 04-Jun-2024
Physical Peramenters