Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.13 | 2.13 | 1.000 | 1.13 | 1.130 | 0.000 |
59W2198 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-47887 दिनांक 04.10.2023
TS Amount (lakhs) : 89.35 Lacs
Financial Detail
Sanction Cost : 89.35 Lacs
Resanction Cost : 89.35 Lacs
Exp. Upto Last Fy : 39.03 Lacs
For CFY 2024-2025
Remaining : 50.32 Lacs
Demand : 50.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 39.03 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 55 %
Sanction on :
7 months 2 weeks ago
04 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.00 किमी0 में सी0सी0 टाईल्स कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 30-Mar-2024