Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.225 | 1.225 | 0.100 | 1.125 | 1.125 | 1.125 |
59W2203 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-58709 दिनांक 11.10.2023
TS Amount (lakhs) : 40.38 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
40.38
Resanction Cost :
40.38
Tentative Cost :
40.38
Exp. Upto Last Fy : 1.61
For CFY 2024-2025
Remaining : 38.77
Demand : 38.00
Allotment : 15.41
Exp in CFY : 15.41
Total Up to Date Exp : 17.01
Work completed
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 100 %
Sanction on :
9 months 6 days ago
11 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2024 -- as on 27-Jun-2024