Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.06 | 1.06 | 0.000 | 1.06 | 1.060 | 0.500 |
59W2211 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55552 दिनांक 30.10.2023
TS Amount (lakhs) : 27.77 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.77
Resanction Cost :
27.77
Tentative Cost :
27.77
Exp. Upto Last Fy : 0.04
For CFY 2024-2025
Remaining : 27.73
Demand : 25.00
Allotment : 10.22
Exp in CFY : 10.22
Total Up to Date Exp : 10.26
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 47 %
Sanction on :
8 months 2 weeks ago
30 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.500 किमी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 27-Jun-2024
Physical Peramenters