Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.355 | 1.355 | 0.000 | 1.355 | 1.000 | 1.355 |
59W2215 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667 दिनांक 27.10.2023
TS Amount (lakhs) : 59.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.89
Resanction Cost :
59.89
Tentative Cost :
59.89
Exp. Upto Last Fy : 2.01
For CFY 2024-2025
Remaining : 57.88
Demand : 45.00
Allotment : 0.39
Exp in CFY : 40.39
Total Up to Date Exp : 42.40
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 95 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
1 day 19 hours from now
19 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर बी0एम0 एवं एस0डी0बी0सी0 का कार्यपूर्ण, रोड़ फर्नीचर का कार्य प्रगति में। -- as on 27-Jun-2024
Physical Peramenters