Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.125 | 1.125 | 0.000 | 1.125 | 1.125 | 1.000 |
59W2217 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-57969 दिनांक 01.11.2023
TS Amount (lakhs) : 66.02 Lacs
Financial Detail
Sanction Cost : 66.02 Lacs
Resanction Cost : 66.02 Lacs
Exp. Upto Last Fy : 25.49 Lacs
For CFY 2024-2025
Remaining : 40.53 Lacs
Demand : 40.00 Lacs
Allotment : 40.00 Lacs
Exp in CFY : 0.86 Lacs
Total Up to Date Exp : 26.35 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 54 %
Up to Date : 89 %
Sanction on :
6 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.00 किमी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 03-May-2024
Physical Peramenters