Work Profile Report [59W2217]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-57969 दिनांक 01.11.2023
TS Amount (lakhs) : 66.02 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.02
Resanction Cost :
66.02
Tentative Cost :
66.02
Exp. Upto Last Fy :
25.49
For CFY 2024-2025
Remaining :
40.53
Demand :
40.00
Allotment :
15.86
Exp in CFY :
15.86
Total Up to Date Exp :
41.35
Construction Started
Sanction on : 1 year 3 weeks ago
01 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
54 %
Up to Date :
98 %
Tentative Completion date on : 2 months 6 days ago
17 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.10 किमी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 04-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: