Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.125 | 1.125 | 0.000 | 1.125 | 1.125 | 1.100 |
59W2217 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-57969 दिनांक 01.11.2023
TS Amount (lakhs) : 66.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
66.02
Resanction Cost :
66.02
Tentative Cost :
66.02
Exp. Upto Last Fy : 25.49
For CFY 2024-2025
Remaining : 40.53
Demand : 40.00
Allotment : 35.86
Exp in CFY : 14.86
Total Up to Date Exp : 40.36
Construction Started
Physical Progress:
At start of FY 2024-2025 : 54 %
Up to Date : 98 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
1 month 4 weeks from now
17 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.10 किमी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 04-Jun-2024
Physical Peramenters