Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.762 | 0.762 | 0.000 | 0.762 | 0.760 | 0.000 |
59W2218 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-57969 दिनांक 01.11.2023
TS Amount (lakhs) : 24.24 Lacs
Financial Detail
Sanction Cost : 24.24 Lacs
Resanction Cost : 24.24 Lacs
Exp. Upto Last Fy : 13.27 Lacs
For CFY 2024-2025
Remaining : 10.97 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 13.27 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
6 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इन्टर कोट तक कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 05-Jan-2024
Physical Peramenters