Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.762 | 0.762 | 0.000 | 0.762 | 0.760 | 0.000 |
59W2218 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-57969 दिनांक 01.11.2023
TS Amount (lakhs) : 24.24 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.24
Resanction Cost :
24.24
Tentative Cost :
24.24
Exp. Upto Last Fy : 13.27
For CFY 2024-2025
Remaining : 10.97
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 13.27
Work completed
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 100 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इन्टर, टाॅप कोट का कार्य विभाग द्वारा पूर्ण किया गया है तथा मार्ग पर पी0सी0 का कार्य आर्मी कंटोनमेन्ट बोर्ड द्वारा स्वंय कराया गया है। (कार्यपूर्ण) -- as on 04-Jun-2024
Physical Peramenters