Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.25 | 1.25 | 0.000 | 1.25 | 1.250 | 0.400 |
59W2219 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55552 दिनांक 29.11.2023
TS Amount (lakhs) : 32.74 Lacs
Financial Detail
Sanction Cost : 32.74 Lacs
Resanction Cost : 32.74 Lacs
Exp. Upto Last Fy : 12.73 Lacs
For CFY 2024-2025
Remaining : 20.01 Lacs
Demand : 12.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.44 Lacs
Total Up to Date Exp : 13.16 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 32 %
Sanction on :
5 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.400 किमी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 03-May-2024
Physical Peramenters