Work Profile Report [59W2229]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई0 फाईल संख्या- 47887/28 दिनांक 24.01.2024
TS Amount (lakhs) : 93.69 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
93.69
Resanction Cost :
93.69
Tentative Cost :
93.69
Exp. Upto Last Fy :
0.08
For CFY 2024-2025
Remaining :
93.61
Demand :
70.00
Allotment :
17.06
Exp in CFY :
23.84
Total Up to Date Exp :
23.92
Construction Started
Sanction on : 11 months 23 hours ago
24 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
54 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
54 प्रतिशत कार्यपूर्ण, शेष कार्य प्रगति पर है। -- as on 20-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand