Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.67 | 1.67 | 0.500 | 1.17 | 1.170 | 0.000 |
59W2231 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई0 फाईल संख्या- 50282 दिनांक 24.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 81.99 Lacs
Resanction Cost : 81.99 Lacs
Exp. Upto Last Fy : 20.90 Lacs
For CFY 2024-2025
Remaining : 61.09 Lacs
Demand : 40.00 Lacs
Allotment : 40.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 20.90 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
3 months 3 weeks ago
24 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
500 मी0 में सी0सी0 इन्टरलोकिंग टाईल्स कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 28-Mar-2024
Physical Peramenters