Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.67 | 1.67 | 0.500 | 1.17 | 1.170 | 0.700 |
59W2231 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई0 फाईल संख्या- 50282 दिनांक 24.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
81.99
Resanction Cost :
81.99
Tentative Cost :
81.99
Exp. Upto Last Fy : 20.90
For CFY 2024-2025
Remaining : 61.09
Demand : 40.00
Allotment : 40.00
Exp in CFY : 3.32
Total Up to Date Exp : 24.22
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 72 %
Sanction on :
5 months 3 weeks ago
24 Jan 2024
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.20 किमी0 में सी0सी0 इन्टरलोकिंग टाईल्स कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 27-Jun-2024
Physical Peramenters