Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.548 | 0.548 | 0.200 | 0.348 | 0.348 | 0.348 |
59W2232 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-53351/29 दिनांक 31.01.2024
TS Amount (lakhs) : 17.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.84
Resanction Cost :
17.84
Tentative Cost :
17.84
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 17.84
Demand : 13.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 37 %
Up to Date : 100 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
3 weeks 1 day ago
25 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2024 -- as on 27-Jun-2024
Physical Peramenters