Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.51 | 0.51 | 0.200 | 0.31 | 0.310 | 0.310 |
59W2236 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-53351/29 दिनांक 31.01.2024
TS Amount (lakhs) : 29.17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.17
Resanction Cost :
29.17
Tentative Cost :
29.17
Exp. Upto Last Fy : 0.16
For CFY 2024-2025
Remaining : 29.01
Demand : 20.00
Allotment : 17.57
Exp in CFY : 17.57
Total Up to Date Exp : 17.74
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 100 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 04/2024 -- as on 03-May-2024
Physical Peramenters