Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.84 | 0.84 | 0.000 | 0.84 | 0.840 | 0.100 |
59W2237 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-53351/29 दिनांक 31.01.2024
TS Amount (lakhs) : 32.98 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
32.98
Resanction Cost :
32.98
Tentative Cost :
32.98
Exp. Upto Last Fy : 0.33
For CFY 2024-2025
Remaining : 32.65
Demand : 24.00
Allotment : 20.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.33
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 15 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 02-Mar-2024
Physical Peramenters