Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.74 | 1.74 | 0.500 | 1.24 | 1.240 | 0.900 |
59W2238 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-53351/29 दिनांक 31.01.2024
TS Amount (lakhs) : 65.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
65.07
Resanction Cost :
65.07
Tentative Cost :
65.07
Exp. Upto Last Fy : 38.25
For CFY 2024-2025
Remaining : 26.82
Demand : 10.00
Allotment : 0.00
Exp in CFY : 9.05
Total Up to Date Exp : 47.30
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 80 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.40 किमी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 04-Jun-2024
Physical Peramenters