Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.884 | 0.884 | 0.000 | 0.884 | 0.884 | 0.300 |
59W2242 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या- 55435/30 दिनांक 31.01.2024
TS Amount (lakhs) : 81.81 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
81.81
Resanction Cost :
81.81
Tentative Cost :
81.81
Exp. Upto Last Fy : 0.76
For CFY 2024-2025
Remaining : 81.05
Demand : 60.00
Allotment : 60.00
Exp in CFY : 21.86
Total Up to Date Exp : 22.62
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 35 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
2 months 6 days from now
24 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
300 मी0 लम्बाई में इन्टरलोकिंग टाईल्स कार्यपूर्ण, शेष कार्य प्रगति मे। -- as on 01-Jul-2024