Work Profile Report [59W2242]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या- 55435/30 दिनांक 31.01.2024
TS Amount (lakhs) : 81.81 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.81
Resanction Cost :
81.81
Tentative Cost :
81.81
Exp. Upto Last Fy :
0.76
For CFY 2024-2025
Remaining :
81.05
Demand :
80.00
Allotment :
33.32
Exp in CFY :
33.32
Total Up to Date Exp :
34.07
Construction Started
Sanction on : 9 months 3 weeks ago
31 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
85 %
Tentative Completion date on : 1 month 4 weeks ago
24 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
750 मी0 लम्बाई में इन्टरलोकिंग टाईल्स कार्यपूर्ण, शेष कार्य प्रगति मे। -- as on 28-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: