Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.81 | 0.81 | 0.300 | 0.51 | 0.510 | 0.510 |
59W2244 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या- 55435/30 दिनांक 31.01.2024
TS Amount (lakhs) : 55.98 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
55.98
Resanction Cost :
55.98
Tentative Cost :
55.98
Exp. Upto Last Fy : 0.33
For CFY 2024-2025
Remaining : 55.65
Demand : 42.00
Allotment : 22.53
Exp in CFY : 22.53
Total Up to Date Exp : 22.86
Work completed
Physical Progress:
At start of FY 2024-2025 : 37 %
Up to Date : 100 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2024 -- as on 27-Jun-2024
Physical Peramenters