Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.81 | 0.81 | 0.300 | 0.51 | 0.510 | 0.400 |
59W2244 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या- 55435/30 दिनांक 31.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 55.98 Lacs
Resanction Cost : 55.98 Lacs
Exp. Upto Last Fy : 0.33 Lacs
For CFY 2024-2025
Remaining : 55.65 Lacs
Demand : 42.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.33 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 37 %
Up to Date : 86 %
Sanction on :
3 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
700 मीटर लम्बाई में कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 03-May-2024
Physical Peramenters