Work Profile Report [59W2250]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-51871/31 दिनांक 06.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1633.29
Resanction Cost :
1633.29
Tentative Cost :
1633.29
Exp. Upto Last Fy :
1,152.49
For CFY 2025-2026
Remaining :
480.80
Demand :
479.80
Allotment :
479.80
Exp in CFY :
290.73
Total Up to Date Exp :
1,443.23
Work completed
Sanction on : 1 year 5 months ago
06 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
69 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 day ago
07 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 07/2025 -- as on 29-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: