Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.000 | 0.000 |
59W2253 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-66213/28 दिनांक 07.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
92.82
Resanction Cost :
92.82
Tentative Cost :
92.82
Exp. Upto Last Fy : 0.83
For CFY 2024-2025
Remaining : 91.99
Demand : 70.00
Allotment : 0.19
Exp in CFY : 0.19
Total Up to Date Exp : 1.02
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 months 1 week ago
07 Mar 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य की ई-निविदा पुनः दि0 06.06.2024 को आमंत्रित, जो दि0 01.07.2024 को प्राप्त कर खोली जानी थी, परन्तु स्थानीय ठेकेदारो द्वारा रायल्टी की दरों में वृद्धि के फलस्वरूप इन निविदाओं का बहिष्कार किया जा रहा है। अब ठेकेदारों से वार्ता के उपरान्त निविदा दि0 22.07.2024 को प्राप्त की जानी है। -- as on 29-Jun-2024
Physical Peramenters