Work Profile Report [59W2372]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667/31 दि0 26.08.2025
TS Amount (lakhs) : 89.45 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.45
Resanction Cost :
89.45
Tentative Cost :
89.45
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
89.45
Demand :
75.00
Allotment :
80.00
Exp in CFY :
39.68
Total Up to Date Exp :
39.68
Construction Started
Sanction on : 3 months 2 weeks ago
26 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
83 %
Tentative Completion date on : 4 months 2 weeks from now
02 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
83 प्रतिशत कार्यपूर्ण। शेष कार्य प्रगति में है। -- as on 28-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand