Work Profile Report [59W2376]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667/31 दि0 26.08.2025
TS Amount (lakhs) : 90.77 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
90.77
Resanction Cost :
90.77
Tentative Cost :
90.77
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
90.77
Demand :
60.00
Allotment :
14.43
Exp in CFY :
14.43
Total Up to Date Exp :
14.43
Construction Started
Sanction on : 3 months 2 weeks ago
26 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
30 %
Tentative Completion date on : 5 months 1 day from now
17 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
30 प्रतिशत कार्यपूर्ण। शेष कार्य प्रगति में है। -- as on 29-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: