Work Profile Report [5W1048]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी बागेश्वर का पत्रांक 593/जि0यो0/प्रशा0/वित्ती0स्वी0/2024-25, दिनांक 31.07.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.00
Resanction Cost :
25.00
Tentative Cost :
25.00
Exp. Upto Last Fy :
9.24
For CFY 2025-2026
Remaining :
15.76
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.24
Construction Started
Sanction on : 9 months 1 week ago
31 Jul 2024
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 03-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: