Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
5W120 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2580/111-2/06-44 (प्रा0आ0)/06दिनांक 19.10.2006
TS Amount (lakhs) : 168.4 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
168.40
Resanction Cost :
168.40
Tentative Cost :
168.40
Exp. Upto Last Fy : 124.33
For CFY 2024-2025
Remaining : 44.07
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 124.33
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
17 years 9 months ago
01 Oct 2006
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मुआवजा वितरण कार्य प्रगति पर। -- as on 13-Jul-2024
Physical Peramenters