Work Profile Report [5W218]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 824/111-2/08-43(एम0एल0ए0)/07 दिनांक 24.03.2008 रू0 61.00 लाख
TS Amount (lakhs) : 441 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
441.00
Resanction Cost :
441.00
Tentative Cost :
441.00
Exp. Upto Last Fy :
294.63
For CFY 2024-2025
Remaining :
146.37
Demand :
92.49
Allotment :
77.78
Exp in CFY :
77.78
Total Up to Date Exp :
372.41
Construction Started
Sanction on : 16 years 9 months ago
24 Mar 2008
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
80 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
6.00 किमी0 पहाड़ कटान एवं 6.00 किमी0 पार्ट-।। कार्य पूर्ण। -- as on 13-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand