Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 6 | 5.500 | 0.5 | 0.500 | 0.000 |
5W218 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 824/111-2/08-43(एम0एल0ए0)/07 दिनांक 24.03.2008 रू0 61.00 लाख
TS Amount (lakhs) : 441 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
441.00
Resanction Cost :
441.00
Tentative Cost :
441.00
Exp. Upto Last Fy : 294.63
For CFY 2024-2025
Remaining : 146.37
Demand : 80.00
Allotment : 51.00
Exp in CFY : 1.69
Total Up to Date Exp : 296.32
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 80 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
6.00 किमी0 पहाड़ कटान एवं 6.00 किमी0 पार्ट-।। कार्य पूर्ण। -- as on 13-Jul-2024
Physical Peramenters