Work Profile

बागेश्वर-देवलधार-मैथाण-लेटी-गिरेछीना मोटर मार्ग का नव निर्माण।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0 824/111-2/08-43(एम0एल0ए0)/07 दिनांक 24.03.2008 रू0 61.00 लाख

TS Amount (lakhs) : 441 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

441.00

Resanction Cost :

441.00

Tentative Cost :

441.00

Exp. Upto Last Fy : 294.63

For CFY 2024-2025

Remaining : 146.37

Demand : 80.00

Allotment : 51.00

Exp in CFY : 1.69

Total Up to Date Exp : 296.32

Construction Started

Physical Progress:

At start of FY 2024-2025 : 75 %

Up to Date : 80 %

Sanction on :
16 years 3 months ago
24 Mar 2008


Tentative Completion date:
Yet To Decide


Actual Completion Date:
Not Yet Reported


Rating : 80

Remark

Forest Status 15: AIP Nodal

Bottelneck: no issue


6.00 किमी0 पहाड़ कटान एवं 6.00 किमी0 पार्ट-।। कार्य पूर्ण। -- as on 13-Jul-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 12 6 5.500 0.5 0.500 0.000
Currently only Bank Gaurantee information is avilable