Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6.000 | 0 | 0.000 | 0.000 |
5W31 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2503/111-(2)/06-37 (प्रा0आ0)/06दिनांक 20.09.2006 एवं 1205/।।।(2)/16-37(प्रा0आ0)/06 टी0सी0-1, दिनांक 29.02.2016
TS Amount (lakhs) : 305.26 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
305.26
Resanction Cost :
305.26
Tentative Cost :
305.26
Exp. Upto Last Fy : 199.26
For CFY 2024-2025
Remaining : 106.00
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 199.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
17 years 9 months ago
20 Sep 2006
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
कार्य पूर्ण। -- as on 29-Aug-2023
Physical Peramenters