Work Profile Report [5W31]

जौलकाण्डे से लेटि तक मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 2503/111-(2)/06-37 (प्रा0आ0)/06दिनांक 20.09.2006 एवं 1205/।।।(2)/16-37(प्रा0आ0)/06 टी0सी0-1, दिनांक 29.02.2016

TS Amount (lakhs) : 305.26 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

305.26

Resanction Cost :

305.26

Tentative Cost :

255.26

Saving

50.00

Exp. Upto Last Fy :

199.26

For CFY 2024-2025

Remaining :

106.00

Demand :

33.60

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

199.26

Work completed

Sanction on : 18 years 3 months ago

20 Sep 2006

Physical Progress:

At start of FY 2024-2025 :

85 %

Up to Date :

100 %

Tentative Completion date on : 4 years 8 months ago

31 Mar 2020

Actual Completion Date : 4 years 8 months ago

31 Mar 2020

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
6.000
0
0.000
0.000

Remark

view all

Overall Saving 50 has been recorded as expected cost of work reduced from 305.26 to 255.26 . -- as on 06-Dec-2024

Rating : 100

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: