Work Profile Report [5W5]

बागेश्वर में हरीनगरी-पय्या मोटर मार्ग का हड़ापडाबू तक विस्तार।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0सं0 2490/111- 2/08-61 (प्रा0आ0)/ 2007 दि0 25.07.2008

TS Amount (lakhs) : 473.11 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

473.11

Resanction Cost :

473.11

Tentative Cost :

473.11

Exp. Upto Last Fy :

469.53

For CFY 2024-2025

Remaining :

3.58

Demand :

3.58

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

469.53

Construction Started

Sanction on : 16 years 3 weeks ago

25 Jul 2008

Physical Progress:

At start of FY 2024-2025 :

85 %

Up to Date :

85 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
9.5
3.000
6.5
0.000
0.000

Remark

view all

3 किमी0 मोटर मार्ग में पहाड़ कटान एवं पार्ट-।। कार्य पूर्ण। किमी0 1 में 8मी0 स्पान आर0सी0सी0 पुलिया एवं किमी0 3 में 24मी0 विस्तार स्टील गर्डर मोटर सेतु का कार्य पूर्ण। -- as on 06-Mar-2024

Rating : 99

Forest Case Pending At : 12: AIP DM

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand