Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
No of Bridges | 2 | 2 | 2 | 0 | 0 | 0 |
5W615 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 671/।।।(2)/16-46(एम.एल.ए.)/2015 टी0सी0, दिनांक 22.03.2016
TS Amount (lakhs) : 305.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
305.76
Resanction Cost :
305.76
Tentative Cost :
305.76
Exp. Upto Last Fy : 268.74
For CFY 2024-2025
Remaining : 37.02
Demand : 10.00
Allotment : 1.00
Exp in CFY : 0.96
Total Up to Date Exp : 269.70
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 3 months ago
22 Mar 2016
Tentative Completion date:
4 years 3 months ago
31 Mar 2020
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। पी0सी0आर0 प्रेषित। मुआवजा प्रस्ताव गठित किया जा रहा है। -- as on 20-Dec-2022
Physical Peramenters